Non Payroll Federal Expenditure Cost Transfer Guidelines
INTERNAL CONTROL GUIDELINES FOR COST TRANSFERS
I. PURPOSE
The Financial Analysis Office has prepared these guidelines to
assist the campus Internal Auditors in their efforts to strengthen the
internal controls over cost transfers to Federal grants and contracts.
The purpose of these guidelines are to provide questions to determine
if the transfer is allowable.
In prior cost transfer audits, the Department of Health and
Human Services found some instances where the University did not
comply with Federal regulations when transferring costs to Federal
projects. The auditors identified unacceptable transfers made:
1. to eliminate cost overruns, 2. to use up unexpended funds,
3. charging projects based on unacceptable allocation methods,
and 4. containing unallowable costs. This situation occurred
because Federal and University guidelines were not consistently
followed. Documentation at the department level was not always
adequate to ensure that the transfers were acceptable.
II. BACKGROUND
Recent Federal audit reports have cited instances where grantees
have transferred costs from other projects or programs to Federal grants
many months after the original charges had been recorded in the grantee's
accounting records. In many cases, the transfers were not supported by
documentation which adequately explained why the transfers were made.
The Federal government recognizes that transfers of costs from one
project to another are occasionally necessary to correct bookkeeping or
clerical errors in the original charges. The Federal government also
recognizes that closely related work may be supported by more than one
funding source and that in such cases a transfer of costs from one
funding source to another may be proper. However, frequent, tardy, and
unexplained (or inadequately explained) transfers, particularly where
they involve projects with significant cost overruns or unexpended fund
balances, raise serious question about the propriety of the transfers
themselves as well as the overall reliability of the grantee's accounting
system and internal controls.
III. REGULATIONS
A. Federal
Federal regulations require that costs claimed on
specific contracts and grants be allocable to the
project being charged. Section C.4. a. of Office
of Management and Budget (OMB) Circular A-21 states:
"A cost is allocable to a particular cost
objective (i.e., a specific function, project,
research agreement, department, or the like)
if the goods or services involved are chargeable
or assignable to such cost objective in
accordance with relative benefits received or
other equitable relationship..."
Section C.4. b. further states that:
"Any costs allocable to a particular sponsored
agreement under the standards provided in this
Circular may not be shifted to other sponsored
agreements in order to meet deficiencies caused
by overruns or other fund considerations, to
avoid restrictions imposed by law or by terms
of the sponsored agreement, or for other reasons
of convenience."
The Public Health Services Grants Administration Manual
provides further guidance regarding the issue of cost
transfers. Chapter 6 of the Manual states that:
"...frequent, tardy, and unexplained (or
inadequately explained) transfers, particularly
where they involve projects with significant cost
overruns or unexpended fund balances, raise
serious questions as to the propriety of the
transfers..."
"The transfers must be supported by documentation
which contain a full explanation of how the
error occurred and a certification of the
correctness of the new charge. An explanation
which merely states that the new transfer was
made "to correct error" or "to transfer to
correct project" is not sufficient..."
B. University
The University guidelines regarding cost transfers are
found in Business and Finance Bulletin A-47 Section V. Page 7
These guidelines require that expenditure adjustments
must be fully explained and justified. In addition,
the Bulletin requires that the campus accounting office
review transfers for compliance with applicable policies
and terms of funding.
IV. COST TRANSFER GUIDELINES
A. General
1. Are formal policies and related procedures
governing cost transfers incorporated in the
campus policies and procedures manual?
2. Have cost transfers been made to, from, or
between Federal awards?
3. Are cost transfers supported by documentation
which adequately explains and justifies why the
transfers were made?
4. Are cost transfers caused by work which is
supported by more than one funding source?
5. Are cost transfers promptly booked?
6. When direct salaries/wages are transferred, is
there a reconciliation between the salaries and
wages transferred and the applicable certified
PAR form?
7. Are interdepartmental cost transfers certified
by both the losing and acquiring department?
8. Are cost transfers dated?
9. Do cost transfers involving Federal grants/contracts
specify the contract and grant numbers, account
and fund numbers of the award?
10. Are cost transfers involving Federal awards
systematically reviewed by the Accounting Office
and/or the Contracts and Grants Office for
adequacy of justification, certification, and
timeliness?
B. Cost Transfer to Correct Errors
1. Are cost transfers to Federal awards which
represent correction of clerical or bookkeeping
errors made promptly after discovery?
2. Are cost transfers of this nature made prior to
submission of expenditure reports to the Federal
government?
3. Are cost transfers supported by documentation
which fully explains how the error was made?
4. Does an appropriate official certify to the
correctness of the new charge?
C. Cost Transfers Resulting from Closely Related Work
When closely related work is supported by more than one
funding source and cost transfers from the originally
charged funding source are made to Federal awards, does
the transfer contain the following:
1. Costs that are allowable charges to the Federal
program?
2. Documentation which includes a full explanation
and justification of the transfer?
3. A certification by the principal investigator or
other responsible official?
4. Review and approval by a responsible financial
or administrative official or the Accounting
Officer?
5. Transfer is completed within 120 days of original
charges?
6. If transfer is not made within 120 days of the
original charge, is an explanation provided?
V. EXAMPLES OF UNALLOWABLE COST TRANSFERS TO FEDERAL PROJECTS
A. TRANSFERS ELIMINATING COST OVERRUNS
Transfers made to shift costs to other sponsored
agreements in order to meet deficiencies caused by
cost overruns are unallowable.
1. Was the cost transferred from a project which
was in an overrun condition?
2. Was the project terminated at the time of the
transfer?
3. Was the project terminated within 120 days of
the transfer?
4. Was the transfer caused by work which was
supported by more than one funding source?
5. Was the work performed under the project charged
closely related to the work performed under the
project originally charged?
6. Were the costs charged to the projects in
proportion to the benefits received by the
project?
7. Was the transfer supported by adequate source
documentation (i.e., timesheets, vouchers,
acceptable allocation procedures, etc.)?
C. TRANSFERS CHARGING PROJECTS BASED ON UNALLOWABLE
ALLOCATION METHODS
Transfers based on an unacceptable allocation basis are
unallowable. The allocation of costs between projects
must be reasonable and in realistic proportion to the
benefit provided or equitable relationship.
1. Was the allocation method used equitable, (i.e.,
did it result in overcharges to the project)?
2. Were the costs charged to the project in
proportion to the benefits received by the
project?
D. TRANSFERS CONTAINING UNALLOWABLE COSTS
Transfers that contain unallowable costs are unallowable.
1. Were the costs transferred allowable charges to
Federal programs under OMB Circular A-21?
2. Were the costs transferred in accordance with
the budget provision of the award?
3. Were the costs transferred allowable under the
award with prior approval?
PHS GRANTS POLICY STATEMENT MANUAL 7-18
COST TRANSFERS
Transfers of cost to, or from grant-supported projects or
programs may sometimes be necessary to correct bookkeeping or clerical
errors in original charges.
Transfers of costs to PHS grants by grantees, subgrantees and
contractors under grants that represent corrections of clerical or
bookkeeping errors must be made promptly after the error is discovered.
The transfers must be supported by documentation that contains a full
explanation of how the error occurred and a certification of the
correctness of the new charge by a responsible financial or
administrative official of the recipient organization. An explanation
which merely states that the transfer was made "to correct error" or
"to transfer to correct project" is not sufficient. It should be noted
that frequent errors in the recording of costs may indicate the need for
improvements in the grantee's accounting system and/or internal controls.
Therefore, where such errors occur, grantees are encouraged and may be
required to evaluate the need for improvements in these areas and to
make what improvements are deemed necessary.
Health professions capitation grants are not subject to the
policy stated above because of the general support nature of these
awards and the latitude and flexibility allowed recipients in the use
of these funds.
Documentation of cost transfers by grantees must be maintained
and be made available for audit review pursuant to 45 CFR 74, Subpart
D (see "Postaward Administration-Record Retention and Access").
CLOSELY-RELATED WORK
When closely-related work is supported by more than one funding
source, the grantee may transfer costs from the originally charged
funding source to a PHS grant, or between PHS grants, with written prior
approval from the PHS awarding office Grants Management Officer,
provided all of the following conditions are met:
1. The projects are scientifically and technically related;
2. The projects are under the direction of the same
principal investigator;
3. The projects have been funded by the same PHS awarding
office;
4. There is no change in the scope of the individual grants
involved;
5. The relating of costs will not be detrimental to the
conduct of work approved under each individual award; and
6. The relatedness will not be used to circumvent the
terms and conditions of an individual award.
PHS GRANTS POLICY STATEMENT MANUAL 7-19
APPLICABLE CREDITS
The term "applicable credits" refers to those receipt or negative
expenditure types of transactions that operate to offset or reduce
expensive items that are allocable to grant-supported projects and
activities as direct or indirect costs. Typical examples are purchase
discounts, rebates, allowances, recoveries or indemnities on losses and
adjustments or overpayments or erroneous charges.
Applicable credits to direct charges made to PHS grants must be
treated as an adjustment on the grantee's Financial Status Report,
whether those credits accrue during or after the period of grant support.
The PHS awarding office will notify the grantee of any additional
actions that may be necessary (see "Postaward Administration Reporting-
Expenditure Report").
COST TRANSFERS MUST MEET THE FOLLOWING CRITERIA:
1. COSTS MUST BE A PROPER AND ALLOWABLE CHARGE OF THE
PROJECT TO WHICH IT IS TRANSFERRED.
2. THE TRANSFER MUST BE SUPPORTED BY DOCUMENTATION WHICH
CONTAINS A FULL EXPLANATION AND JUSTIFICATION FOR THE
TRANSFER.
3. THE TRANSFER MUST BE CERTIFIED BY A RESPONSIBLE PROGRAM
OFFICIAL AS TO IT'S PROPRIETY.
4. THE TRANSFER MUST BE APPROVED BY AN ADMINISTRATIVE
OFFICIAL OF THE UNIVERSITY (ACCOUNTING OFFICE).
5. THE TRANSFER SHOULD BE MADE WITHIN 120 DAYS OF THE
ORIGINAL CHARGE. IF THE TRANSFER IS DONE AFTER THIS
PERIOD OF TIME, IT MUST INCLUDE AN ADDITIONAL EXPLANATION
AS TO WHY THE TRANSFER WAS LATE.